Phoenix House Dormitory Conversion

DKP, in cooperation with the owner, completed a feasibility analysis that indicated a need for the transfer of teens to a separate dormitory facility. To address that need, DKP converted an existing building. The project was completed with a negotiated general contract and the assistance of over 300 volunteers from Corporate Volunteers. DKP produced the preliminary and CDD plans, and the project was completed within 94 days.

Administration Building

Date of Completion: 1996
Location: Santa Ana, California
Scope of Work: Feasibility analysis; design, and full service documents for the conversion of and administration building to a teen dormitory and housing administration building.
Client: Phoenix Houses of California
Status: Complete
Building Area: 980 square feet
Site Area: 6.2 acre
Team Members: (DKP) Donald Krotee, Matt Rogers